Utility Dive•about 1 month ago
AEP eyes exit from PJM, SPP over slow generation interconnection
- •AEP is considering exiting PJM and SPP due to severe delays in generation interconnection, signaling critical frustration with current RTO processes.
- •AEP's utilities have contracted for an unprecedented 63 GW of new large load by 2030, highlighting massive demand growth, likely driven by datacenters and industrial expansion.
- •This situation underscores significant challenges for developers in PJM and SPP regarding project viability and grid access, and for large loads in securing timely and reliable power.